Most site selection mistakes in Mexico don’t announce themselves. They hide inside decisions that looked perfectly reasonable at the time — a great-looking building in a corridor that can’t deliver the power, a lease signed before the entry model was settled, a shortlist built from listing PDFs instead of verified utility data.
(The universal site selection experience: the building that seemed perfect until you read the CFE footnote. We have seen this happen. Multiple times. From both sides of the table.)

What Are the Five Site Selection Mistakes That Actually Cost Money in Mexico?
The five site selection mistakes that cost money in Mexico are choosing a building before confirming power, signing a lease before settling the entry model, evaluating sites on a generic regional basis instead of scoring labor locally, skipping lease milestone protection, and treating site selection as the final decision instead of the first step in a longer softlanding.
| Mistake | The Cost |
|---|---|
| Choosing a building before confirming power | Lease obligation on a site that may take longer to power than to build |
| Signing a lease before settling entry model | Lease milestones don’t match the actual permitting path |
| Evaluating sites on a generic regional basis | Missing labor saturation that varies within the same corridor |
| Skipping lease milestone protection | All financial exposure, no execution protection |
| Treating site selection as the final decision | A site that can’t be operationalized on schedule isn’t a win |
The diligence that prevents these mistakes
our softlanding checklist is built specifically for this stage — the questions that distinguish a verified site from one that looks right but has a problem nobody flagged. site selection experts who have done this before know which footnotes to read, and our site selection page lays out the full scoring model.
talk to a softlanding lead before you shortlist, and we’ll flag these risks before they become problems.
Frequently Asked Questions
What is the single costliest site selection mistake in Mexico?
Choosing a building before confirming power. Getting CFE to commit a multi-megawatt feed can take longer than the entire construction timeline at some parks.
Why does labor market evaluation need to happen at the park level, not the regional level?
Labor markets vary dramatically within a single corridor. Two parks in the same city can serve completely different labor pools.
Is site selection the final step in a Mexico expansion?
No. The site is step one. The softlanding, permits, power, workforce, is everything that follows, and a site that cannot be operationalized on schedule is not a real estate win.
How can manufacturers avoid the entry-model timing mistake?
Decide shelter versus standalone IMMEX before signing a lease, so lease milestones reflect the actual permitting path instead of a generic template.