Delays in Mexico are rarely dramatic. Nobody’s plant gets stuck because of a single catastrophic failure — it’s death by a thousand small waits, each one reasonable on its own, that together add four to six months to a schedule that was supposed to take twelve.
(The unofficial motto of every delayed plant opening: “it’s basically done.” It is never basically done.)

Where Do the Costly Delays Actually Come From When Opening a Facility in Mexico?
Costly delays come from three sources: a power feed CFE hadn’t actually committed to, a permit that quietly depended on a different permit nobody tracked, and a workforce plan that started the week the building was finished instead of three months before.
Three sources account for most of it: a power feed that CFE hadn’t actually committed to, a permit that quietly depended on a different permit nobody tracked, and a workforce plan that started the week the building was finished instead of three months before.
| Delay Source | The Fix |
|---|---|
| Unconfirmed power feed | Get a CFE commitment in writing before committing |
| Untracked permit dependency | Map dependencies before the first filing |
| Late workforce plan | Start recruiting three months before completion, not the week of |
The fix is sequencing, not speed
None of this gets solved by working faster on any one task. It gets solved by mapping dependencies before you start — the same approach we lay out in what a softlanding actually means — so permitting and construction and recruiting are scheduled against each other, not against wishful thinking.
Building this into your IMMEX timeline
Whether you’re entering through a shelter company or a standalone IMMEX program program (shelter vs. standalone IMMEX breaks down that decision), the permitting clock starts the moment your entity or shelter agreement is in place — not when the building is ready. Start it early. This is the sequencing our softlanding team manages by default.
talk to a softlanding lead before you sign a lease, and we’ll flag the dependencies most teams miss.
Frequently Asked Questions
What are the three most common causes of costly delays in Mexico?
An unconfirmed CFE power feed, an untracked permit dependency, and a workforce plan that starts too late relative to construction completion.
Does working faster on individual tasks fix these delays?
No. The fix is mapping dependencies before you start, so tasks are scheduled against each other rather than against wishful thinking.
When does the IMMEX permitting clock actually start?
The moment your entity or shelter agreement is in place, not when the building is ready. Starting it early avoids a preventable delay.
Is a six-month delay usually one big problem or several small ones?
Several small ones. It almost always shows up as multiple two-week waits that were never flagged early enough to fix.